Plan the first working session
Interview the change coordinator and production planner
Choose a component revision introduced while orders were open. Does it apply by serial number, build order or date, and which stock was already committed?
What the team takes away
An affected-order register names the governing revision and release basis, distinguishing existing commitments from orders the planner should update.
Establish the approved version
Read the approved change notice, released BOM revisions, open production orders and inventory allocations. Retain the approved effectivity rule and any deviation permits.
Where the boundary moves
An order opened before the change contains units on both sides of the serial cutoff. Selecting the BOM solely by order creation date can incorrectly apply one revision to all units.
Resolve applicability
- Identify part revisions touched by the approved change.
- Compare each open order with the effectivity boundary.
- Prepare an affected-order list with shortages, deviations and old stock reserved.
Validate the first change
Replay a change that crossed open orders and include one approved deviation. Confirm order-level and serial-level results before the planning team uses the list during a change meeting.
Measure correction and rework
Measure order corrections after change release, time to locate affected material and instances where the wrong revision reached kitting. Track unused stock separately from production rework.